Construction activity is continuing on programme and there has been significant progress in all areas of the development since our last newsletter. The core walls of the structure have been finished to level 25. Floor slabs have been poured up to level 22 and glazing is in place up to the eighth floor.

The building services installation is progressing well. The principal contractor, MACE, reported a minor delay due to installation issues with cladding steelwork and high winds affecting crane use - these have now been resolved and normal progress has resumed.